Nordion expects reactor decision in September
June 29, 2012 -- Nordion said it expects a decision in September regarding its dispute with Atomic Energy of Canada over a nuclear reactor project.
To view the remainder of this article, and other exclusive content, you must first sign-in or register using the options below.
(Helptag:PaywallArticleLoginMessage)
| |
|
|
New AuntMinnie.com Members
|
Becoming a Member is FREE!
|

Real-time radiology-specific news
Case of the Day and Teaching Files
Focused topics digital communities
Lively, discussion groups
Medical imaging bookstore
SalaryScan
Job Boards
OnLine CMe/CE
Bookstore, market reports, more …
Conference Calendar
User-controlled eNewsletters
… registration is FREE and easy!
|
| |
|
AECL, a Canadian government corporation, was building two new nuclear reactors -- known as the Maple project -- and had a contract to supply Nordion with radioisotopes when they were completed. However, design problems with the reactors delayed the project, and the Canadian government eventually canceled its plans to complete them.
The Maple reactors would have replaced the aging National Research Universal (NRU) reactor, which produces much of North America's supply of molybdenum-99, the precursor to technetium-99m, which is widely used in nuclear cardiology.
Nordion served the Canadian government with a notice of arbitration in 2008 regarding its decision, seeking to compel the government to complete the Maple facilities as well as pay Nordion monetary damages. Arbitration hearings were completed in May 2012.
The arbitration panel plans to render a decision in September, according to Nordion.
| |
|